The houses on the northern side are advancing with the flooring works and have also commenced the putty works after completing the internal plastering.

Courtyard houses are progressing with internal and external plastering, electrical and plumbing work, as well as door and window frame installation.

The podium houses are making progress with the ground floor brickwork and the casting of the ground floor slab.