GoodEarth Motif work in progress – 10 Feb 2023

The piling and footing work is currently being carried out at a swift pace, and we have also started backfilling. In addition, we are making progress on the construction of the pump room, the walls for the rainwater tank, the covering for the raw water tank, and the retaining wall for the basement.

The wall building for the rainwater tank has started

The raw water tank covering has been completed


Shuttering for the retaining wall in the basement area has started

We have completed the casting of the plinth beam for the pump room
Work in progress: Photographs depicting various work in its different stages at Motif project.